Which of the following correctly identifies the application of a project’s quality management plan?

Which of the following correctly identifies the application of a project’s quality management plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality assurance and quality control both occur in the monitoring / controlling phase.

B.
Quality control occurs in the execution phase, quality assurance occurs in the monitoring /
controlling phase.

C.
Quality assurance occurs in the execution phase, quality control occurs in the monitoring /
controlling phase.

D.
Quality assurance and quality control both occur in the execution phase.

2 Comments on “Which of the following correctly identifies the application of a project’s quality management plan?

  1. Michael McNeil says:

    Quality Management Plan
    The quality management plan describes how the project team will carry out the quality
    policy. It documents the outputs from the quality activities that were performed, the
    procedures used to complete the quality activities, and the resources required. This plan
    will be the basis for performing quality control when you are in project execution.
    The procedures section of the plan includes more detailed information regarding
    the expected results from quality activities and the steps used to determine whether the
    quality standards are being met. The quality standards and the method used to measure
    these standards should be clearly defi ned.
    You can use several methods when measuring whether quality standards have been met,
    including metrics, checklists, and exit criteria:
    Quality metrics A quality metric is a standard of measurement that specifi cally
    defi nes what will be measured and how it will be measured. You can defi ne metrics for
    any area of the project. We ’ ll use a web sales application as an example. If you ’ re going to
    measure quality of the checkout process, your metric might state that when the customer
    implements the checkout process, the system will multiply the price of each item by the
    quantity of items ordered and compute the applicable sales tax and shipping charges
    100 percent of the time. This metric would be part of the test scenarios used in the user
    acceptance test.
    Quality checklists A quality checklist is a tool that lists a series of steps that must be
    taken to complete an activity or process. As each step is completed, it is marked off the list.
    This provides documentation that the steps were completed and can also be used to track
    when the step was taken and who performed the work.
    Exit criteria Your project may include exit criteria that must be met at the completion
    of the project. Or, if you ’ re using milestones to mark the end of one project phase and
    the beginning of the next phase, the milestones between phases may include quality exit
    criteria. In this case, your quality plan should document the criteria that must be met at
    each phase to consider that phase complete. Software development projects frequently use
    a series of tests to confi rm the quality of the major deliverables for each phase. These tests
    can be established as exit criteria.
    The quality management plan should also address how the results of the quality
    activities will be reviewed with the project sponsor and other stakeholders. Identifi cation
    of any quality activities requiring formal sign – off are also documented in the plan.




    0



    0
  2. Steve says:

    Questions 233. Which of the following correctly identifies the application of a projects quality management plan?
    A. Quality assurance and quality control both occur in the monitoring / controlling phase.
    B. Quality control occurs in the execution phase, quality assurance occurs in the monitoring / controlling phase.
    C. Quality assurance occurs in the execution phase, quality control occurs in the monitoring / controlling phase.
    D. Quality assurance and quality control both occur in the execution phase.

    Answer: C