After a change control Board meeting, which of the following actions should the project manager
do NEXT?

A.
Notify the requester of the verdict.
B.
Review the impact of proposed change.
C.
Update the project scope statement.
D.
Document the specific change request.
Answer is A
After the change control board meeting, the project manager should notify the requester of the CCB (change control board) verdict to approve or deny the change.
After the change has been approved by the CCB, the project scope statement must be modified and agreed to in writing by obtaining a sign-off.
Before conducting the change control board meeting, the project manager should review any impact of the proposed change.