How will this impact the project?

A project manager learns that a key staff member is making unauthorized product changes. How
will this impact the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality standards will improve

B.
Scope creep will occur

C.
Risks will decrease

D.
Acceptance testing will decrease

Explanation: