PrepAway - Latest Free Exam Questions & Answers

Who is responsible for the overall direction, costs, and timetables for systems-development project

Who is responsible for the overall direction, costs, and timetables for systems-development
projects?

PrepAway - Latest Free Exam Questions & Answers

A.
The project sponsor

B.
The project steering committee

C.
Senior management

D.
The project team leader

Explanation:
The project steering committee is responsible for the overall direction, costs, and
timetables for systems-development projects.


Leave a Reply