When should application controls be considered within the system-development process?

When should application controls be considered within the system-development process?

PrepAway - Latest Free Exam Questions & Answers

A.
After application unit testing

B.
After application module testing

C.
After applications systems testing

D.
As early as possible, even in the development of the project’s functional specifications

Explanation:
Application controls should be considered as early as possible in the systemdevelopment process, even in the development of the project’s functional specifications.