Which of the following should be included in a feasibility study for a project to implement an EDI process?

Which of the following should be included in a feasibility study for a project to implement an EDI
process?

PrepAway - Latest Free Exam Questions & Answers

A.
The encryption algorithm format

B.
The detailed internal control procedures

C.
The necessary communication protocols

D.
The proposed trusted third-party agreement

Explanation:

Encryption algorithms, third-party agreements and internal control procedures are too detailed for
this phase. They would only be outlined and any cost or performance implications shown. The

communications protocols must be included, as there may besignificant cost implications if new
hardware and software are involved, and risk implications if the technology is new to the
organization.