When reviewing a project where quality is a major concern, an IS auditor should use the project
management triangle to explain that:

PrepAway - Latest Free Exam Questions & Answers

A.
increases in quality can be achieved, even if resource allocation is decreased.

B.
increases in quality are only achieved if resource allocation is increased.

C.
decreases in delivery time can be achieved, even if resource allocation is decreased.

D.
decreases in delivery time can only be achieved if quality is decreased.

Explanation:

The three primary dimensions of a project are determined by the deliverables, the allocated
resources and the delivery time. The area of the project management triangle, comprised of these
three dimensions, is fixed. Depending on the degree of freedom, changes in one dimension might
be compensated by changing either one or both remaining dimensions. Thus, if resource
allocation is decreased an increase in quality can be achieved, if a delay in the delivery time of the
project will be accepted. The area of the triangle always remains constant.