which of the following phases in system development would user acceptance test plans normally be prepared?

During which of the following phases in system development would user acceptance test plans

normally be prepared?

PrepAway - Latest Free Exam Questions & Answers

A.
Feasibility study

B.
Requirements definition

C.
implementation planning

D.
Postimplementation review

Explanation:

During requirements definition, the project team will be working with the users to define their
precise objectives and functional needs. At this time, the users should be working with the team to
consider and document how the system functionality canbe tested to ensure it meets their stated
needs. The feasibility study is too early for such detailed user involvement, and the implementation
planning and postimplementation review phases are too late. An IS auditor should know at what
point user testing should be planned to ensure it is most effective and efficient.