Which of the following activities should the business continuity manager perform FIRST after the replacement o

Which of the following activities should the business continuity manager perform FIRST after the
replacement of hardware at the primary information processing facility?

PrepAway - Latest Free Exam Questions & Answers

A.
Verify compatibility with the hot site.

B.
Review the implementation report.

C.
Perform a walk-through of the disaster recovery plan.

D.
Update the IS assets inventory.

Explanation:

An IS assets inventory is the basic input for the business continuity/disaster recovery plan, and the
plan must be updated to reflect changes in the IS infrastructure. The other choices are procedures
required to update the disaster recovery plan after having updated the required assets inventory.