Which of the following would have the HIGHEST priority in a business continuity plan (BCP)?

Which of the following would have the HIGHEST priority in a business continuity plan (BCP)?

PrepAway - Latest Free Exam Questions & Answers

A.
Resuming critical processes

B.
Recovering sensitive processes

C.
Restoring the site

D.
Relocating operations to an alternative site

Explanation:

The resumption of critical processes has the highest priority as it enables business processes to
begin immediately after the interruption and not later than the declared mean time between failure
(MTBF). Recovery of sensitive processes refers to recovering the vital and sensitive processes
that can be performed manually at a tolerable cost for an extended period of time and those that
are not marked as high priority. Repairing and restoring the site to original status and resuming the
business operations are time consuming operations and are not the highest priority. Relocating
operations to an alternative site, either temporarily or permanently depending on the interruption,
is a time consuming process; moreover, relocation may not be required.