When developing a disaster recovery plan, the criteria for determining the acceptable downtime should be the:

When developing a disaster recovery plan, the criteria for determining the acceptable downtime
should be the:

PrepAway - Latest Free Exam Questions & Answers

A.
annualized loss expectancy (ALE).

B.
service delivery objective.

C.
quantity of orphan data.

D.
maximum tolerable outage.

Explanation:

The recovery time objective is determined based on the acceptable downtime in case of a
disruption of operations, it indicates the maximum tolerable outage that an organization considers
to be acceptable before a system or process must resume following a disaster. Choice A is
incorrect, because the acceptable downtime would not be determined by the annualized loss
expectancy (ALE). Choices B and C are relevant to business continuity, but they are not
determined by acceptable downtime.