The software quality process MOST recently added by the organization is:

An IS auditor is told by IS management that the organization has recently reached the highest
level of the software capability maturity model (CMM). The software quality process MOST
recently added by the organization is:

PrepAway - Latest Free Exam Questions & Answers

A.
continuous improvement.

B.
quantitative quality goals.

C.
a documented process.

D.
a process tailored to specific projects.

Explanation:

An organization would have reached the highest level of the software CMM at level 5, optimizing.
Quantitative quality goals can be reached at level 4 and below, a documented process is executed
at level 3 and below, and a process tailored to specific projects can be achieved at level 3 or
below.