PrepAway - Latest Free Exam Questions & Answers

Which of the following would the project manager MOST l…

A project team member highlights to the project manager that expensive licensing for critical
software in use across the project may exp.re before the completion of the project. Which of the
following would the project manager MOST likely do?

PrepAway - Latest Free Exam Questions & Answers

A.
Place a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or
mitigate the risk.

B.
Raise a purchase order to purchase the licensing and ask the team member to install it.

C.
Amend the project scope and raise a project change request to obtain approval of the amendment.

D.
Amend the project schedule and work breakdown structures to remove the use of the software from the project.


Leave a Reply