A new project sponsor has joined the project team, and the constraints on the project have been
reprioritized. The project cost was previously the most important factor, but the new sponsor has
indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this
MOST likely to have on the project?

PrepAway - Latest Free Exam Questions & Answers

A.
The deliverables and quality will remain the same, but the cost will increase.

B.
The deliverables and quality will remain the same, but the cost will decrease.

C.
The deliverables and cost will remain the same, but the quality will increase.

D.
The cost and quality will remain the same, but the deliverables will increase.