The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost baseline

B.
Burn rate

C.
Cost variance report

D.
Total project cost