PrepAway - Latest Free Exam Questions & Answers

Which of the following strategies is the project manage…

A project manager noticed the development team supporting a project does not have sufficient
skills to complete the development phase The project manager has discussed this issue with the
functional manager and agreed to continue with the development phase due to time restrictions.
Which of the following strategies is the project manager applying?

PrepAway - Latest Free Exam Questions & Answers

A.
Accepting

B.
Mitigating

C.
Avoiding

D.
Transferring


Leave a Reply