A project team has determined it will need to source data from a system that was not part of the
project scope. The role of the project manager is to analyze which of the following impacts?

PrepAway - Latest Free Exam Questions & Answers

A.
Technical design, schedule, and budget

B.
Business process impacts and resourcing

C.
New software and hardware requirements

D.
Schedule, budget, and quality