Which of the following actions should the project manag…

An authorized change to a construction project was implemented. During the modification, the team
identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?

PrepAway - Latest Free Exam Questions & Answers

A.
Submit a new change request.

B.
Initiate the regression plan.

C.
Add remediation to the schedule.

D.
Accept the new power output.