A new stake holder has joined the project team and requested modifications that will result in minor
changes to the project budget and schedule project manager is concerned that the requests will
lead to ____.

PrepAway - Latest Free Exam Questions & Answers

A.
quality control issues

B.
additional risks

C.
scope creep

D.
time constraints