Which of the following is the FIRST step the project take?

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project take?

PrepAway - Latest Free Exam Questions & Answers

A.
Assess the risk register’s new items.

B.
Review the task start and finish dates.

C.
Obtain additional resources.

D.
Analyze the assigned hours.