PrepAway - Latest Free Exam Questions & Answers

The design activity of a project has the following cost…

The design activity of a project has the following cost attributes:
PV = 100,000
EV = 20,000
AC = 90,000
Based on this scenario, calculate the schedule variance.

PrepAway - Latest Free Exam Questions & Answers

A.
-80,000

B.
-70,000

C.
10,000

D.
120,000


Leave a Reply