PrepAway - Latest Free Exam Questions & Answers

Which of the following are critical for the project man…

A project manager provides status reports to a customer on a biweekly basis, but the customer is
very busy and only has a few minutes to review the project. Which of the following are critical for
the project manager to provide?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost, schedule, organizational chart, and risks/issues

B.
Risk/issues, cost, RAO chart, and action items

C.
Schedule, cost, risk/issues, and milestones

D.
Action items, organizational chart, schedule, and NDA


Leave a Reply