A program manager informs a project manager that a new, high-priority project has been approved
and will need the current project’s resources before the scheduled project close- date The project
team meets and determines that the project should be fast-tracked. Which of the following
documents should the project team reference to fast-track the project? (Select TWO.)

PrepAway - Latest Free Exam Questions & Answers

A.
Scope management plan

B.
Configuration management plan

C.
Network diagram

D.
Project schedule

E.
Project plan