A senior manager asks a project manager for an estimated budget on a new project. Which of the
following is the BEST step for the project manager to take?

PrepAway - Latest Free Exam Questions & Answers

A.
Tell the senior manager the estimation is not available yet.

B.
Use the budget from a similar project to generate estimates.

C.
Ask a SME for an opinion and propose an estimate.

D.
Gather the team to immediately generate estimates.