PrepAway - Latest Free Exam Questions & Answers

which of the following is the BEST approach to find thi…

If a project sponsor wants to know the current status and progress of a project, which of the
following is the BEST approach to find this information?

PrepAway - Latest Free Exam Questions & Answers

A.
The project sponsor should obtain the current status from team members, put it into a presentation, and present
it to the project manager for review.

B.
The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and
run a report.

C.
The scheduler should obtain the current status from team members, update the project charter, project
management plan, dashboard, and SOW; and then create a status report to provide to the project manager.

D.
The scheduler should obtain the current status from team members, update the risk register, and provide the
information to the project champion for review.


Leave a Reply