Which of the following should the project manger do NEXT?

A project manger received a change request, immediately documented the required changes, and
evaluated the impact of and justification for the changes. Which of the following should the project
manger do NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Gain approval for the changes.

B.
Identify the approval authority.

C.
Implement the changes.

D.
Create an emergency change request.