Which of the following tools and techniques of the Define Activity process will help you in identifying the ty

You are working as a project manager for BlueWell Inc. Which of the following tools and
techniques of the Define Activity process will help you in identifying the typical schedule
milestones?

PrepAway - Latest Free Exam Questions & Answers

A.
Expert Judgment

B.
Decomposition

C.
Rolling Wave Planning

D.
Templates

Explanation:
Templates are used to identify the typical schedule milestones in the Define Activity process. The
tools and techniques used in defining the activity process are as follows: Decomposition: It is used
to further divide the project work package into a more smaller and convenient form called
activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work
to be accomplished in the near term is planned in detail and future work is planned at a higher
level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous
project and used in a new project. Expert Judgement: The skilled members in a project team or
other experts who develop project scope statements can help provide knowledge in defining
activities.