The_____ allows the project team to look at the performance of the project to date, and use that data to make

CORRECT TEXT
Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the
performance of the project to date, and use that data to make more accurate projections about the
future.

PrepAway - Latest Free Exam Questions & Answers

Answer: Schedule model