PrepAway - Latest Free Exam Questions & Answers

What is Holly’s schedule variance for this project?

Holly is the project manager of the NDS project and she is 85 percent complete with her project
though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has
spent $8,011,221 to date. What is Holly’s schedule variance for this project?

PrepAway - Latest Free Exam Questions & Answers

A.
$163,626

B.
$130,901

C.
-$985,040

D.
0.16

Explanation:
The schedule variance for a project can be found by subtracting the planned value from the
earned value. In this instance, it would be as follows:
SV = EV – PV
=(0.85*9,850,400) – (0.95*9,850,400)
= 8,372,840 – 9,357,880
=-985,040
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies
that the schedule is ahead or behind what was planned for this period in time. The schedule
variance is calculated based on the following formula: SV = Earned Value (EV) – Planned Value
(PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value
greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that
the project is right on target.
Answer option B is incorrect. $130,901 is the cost variance.
Answer option A is incorrect. $163,626 is the variance at completion for this project.
Answer option D is incorrect. 0.16 is the difference between the schedule performance index of
.84 and a perfect schedule.


Leave a Reply