What does this figure depict?

You work as a project manager for BlueWell Inc. You are calculating the performance indexes of
your project. The cost variance (CV) of your project is 30. What does this figure depict?

PrepAway - Latest Free Exam Questions & Answers

A.
Project is behind the schedule.

B.
Costs are higher than planned.

C.
Costs are right on target.

D.
Costs are lower than planned.

Explanation:
According to the question, the cost variance of the project is 30, which is a positive figure. A
positive value means that cost is less than planned. What is CV? Cost variance (CV) is a measure
of cost performance on a project. The variance notifies if costs are higher than budgeted or lower
than budgeted. The cost variance is calculated based on the following formula: CV = Earned
Value (EV) – Actual Cost (AC) A positive value means that spending is less than budgeted,
whereas a negative value indicates that costs are higher than originally planned for the project.
Answer option C is incorrect. If the CV is zero, it shows that cost is right on target.
Answer option A is incorrect. This result is depicted by viewing the schedule variance (SV), not the
CV.
Answer option B is incorrect. If the CV is a negative value, it depicts that the costs are higher than
planned.