what day of the week will the project end if there are 67 days of project work left to complete?

You are the project manager for your company. You are working with the management regarding
the exact end date of your project. Management needs to know what day of the week your project
will complete. Assuming that your project will not require any work to be completed over the
upcoming weekends and that the remaining project work will commence on a Tuesday, what day
of the week will the project end if there are 67 days of project work left to complete?

PrepAway - Latest Free Exam Questions & Answers

A.
Wednesday

B.
Thursday

C.
Monday

D.
Tuesday

Explanation:
The project will end on a Wednesday. If the project work commences on a Tuesday, there will be
four days to complete in that week. That will bring the project work down to 63 days of remaining
work. Each work week counts as five days of work. 63 divided by 5 is 12 work weeks with three
days remaining. The 63rd remaining day will complete on a Wednesday.
Answer options C, D, and B are incorrect. These are not the valid answers.