What skills should he possess to efficiently work with the project team?

A company hires a scheduler for one of its projects. What skills should he possess to efficiently
work with the project team? Each correct answer represents a complete solution. Choose three.

PrepAway - Latest Free Exam Questions & Answers

A.
Performance control

B.
Execution scheduling

C.
Leadership

D.
Feasibility planning

Explanation:
A scheduler schedules the constraints for the project into phases with respect to the time and
resources available. He can be hired from outside a company, or from within a company. The
basic roles of a scheduler are as follows: Feasibility Planning: A scheduler is the time
management expert who paints a picture of the project. He develops a strategy for delivery and to
gain consensus. Execution Schedule: A scheduler works with the project team to optimize and
refine the schedule until an agreed schedule has been developed. Performance Control: A
schedule is maintained by the scheduler who optimizes outcomes and instructs the project team
on their presentation. It is important that the scheduler be aware of the changes and trends related
to the project delivery.
Answer option C is incorrect. This is the skill possessed by the project manager.