Which of the following is an output of the Develop Schedule process?

You are the project manager for your organization. You and the project team are developing the
project schedule for your current project. This project management process will create four
outputs. Which of the following is an output of the Develop Schedule process?

PrepAway - Latest Free Exam Questions & Answers

A.
Work performance information

B.
Schedule baseline

C.
Resource calendars

D.
Activity duration estimates

Explanation:
The schedule baseline is the only output of the develop schedule process among these answers.
The three other outputs of the Develop Schedule Process are: project schedule, schedule data,
and project document updates.
Answer option D is incorrect. Activity duration estimates are an output of the Estimate Activity
Duration process.
Answer option A is incorrect. Work performance information is an input of the Control Schedule
process.
Answer option C is incorrect. Resource calendars are an input to the Develop Schedule process.