Which of the following is an output of the Identify Stakeholders process?

Which of the following is an output of the Identify Stakeholders process?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope baseline

B.
Project scope statement

C.
Project charter

D.
Stakeholder register

Explanation:
The Identify Stakeholders process identifies all people or organizations that are impacted by the
project. It also documents relevant information regarding their interests, involvement, and impact
on project success. Stakeholder register and stakeholder management strategy are outputs of this
process.
Answer option C is incorrect. Project charter is one of the inputs of the Identify Stakeholders
process.
Answer option A is incorrect. Scope baseline is one of the outputs of the Create Work Breakdown
Structure (WBS) process.
Answer option B is incorrect. Project scope statement is one of the outputs of the Define Scope
process.