Which approach could you use to shorten the duration of the project?

Your project team is executing the project plan and things are going well. Your team has reached
its first milestone and is now in the second phase of the project. The project stakeholders have
requested that you find a method to reduce the duration of the project. They will reward you and
your project team with a 25 percent bonus of the project costs if you can finish the project thirty
days earlier than what was already planned. The stakeholders, however, will not approve any
additional labor costs as part of the agreement. Which approach could you use to shorten the
duration of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform resource leveling for the project.

B.
Crash the project schedule.

C.
Fast track the project.

D.
Remove things from the project scope.

Explanation:
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are
overlapped that would normally be done in sequence. It is shortening the project schedule without
reducing the project scope. It does not add any additional labor but it can introduce project risks.
Answer option D is incorrect. Removing things from the project scope can reduce the project
duration, but it will not satisfy the requirements the stakeholders have identified.
Answer option A is incorrect. Resource leveling can actually increase the project duration.
Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor
expense, something the stakeholders won’t approve.