What is the latest your project team can complete Activity I?

You work as a project manager for BlueWell Inc. By referring to the figure given below, you along
with your project team is calculating the latest completion of an activity.

What is the latest your project team can complete Activity I?

PrepAway - Latest Free Exam Questions & Answers

A.
Day 29

B.
Day 26

C.
Day 25

D.
Day 30

Explanation:
Activity I can actually take all the way to Day 30 to complete. Note in the figure that Activity I does
not need to be completed before Activity K can begin. This allows Activity I to take until Day 30 to
complete as its late finish.
Answer option C is incorrect. This is the earliest Activity I may finish.
Answer options B and A are incorrect. These are not the valid calculation.