What does this figure depict?

You work as a Project Manager for Media Perfect Inc. Several projects are running under your
supervision. Rick, team leader of a project, provides you performance indexes of his project. The
schedule variance (SV) of his project is 25. What does this figure depict?

PrepAway - Latest Free Exam Questions & Answers

A.
Project is behind the schedule.

B.
Costs are higher than planned.

C.
Project is right on target.

D.
Project is ahead of the schedule.

Explanation:
According to the question, the schedule variance (SV) of the project is 25, which is a positive
value. The positive SV depicts that the project is ahead of the planned schedule. What is SV?
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies
that the schedule is ahead or behind what was planned for this period in time. The schedule
variance is calculated based on the following formula: SV = Earned Value (EV) – Planned Value
(PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value
greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that
the project is right on target.
Answer option A is incorrect. The negative SV means that project is behind the schedule.
Answer option C is incorrect. The zero SV means that project is right on target.
Answer option B is incorrect. This result can be drawn by looking at the cost variance (CV) of the
project. What is CV? Cost variance (CV) is a measure of cost performance on a project. The
variance notifies if costs are higher than budgeted or lower than budgeted. The cost variance is
calculated based on the following formula: CV = Earned Value (EV) – Actual Cost (AC) A positive
value means that spending is less than budgeted, whereas a negative value indicates that costs
are higher than originally planned for the project.