PrepAway - Latest Free Exam Questions & Answers

Which of the following is NOT an aim of the Change Management process?

Which of the following is NOT an aim of the Change Management process?

PrepAway - Latest Free Exam Questions & Answers

A.
Overall business riskisoptimised

B.
Standardised methods and procedures are used for efficient and prompt handling of all Changes

C.
All budgets and expenditures are accounted for

D.
All changes to Service Assets and Configuration Items (CIs) are recorded in the Configuration Management system

Explanation: