The group that authorizes changes that must be installed faster than the normal process is called the?

The group that authorizes changes that must be installed faster than the normal process is called the?

PrepAway - Latest Free Exam Questions & Answers

A.
CAB Emergency Committee (CAB/EC)

B.
Emergency CAB (ECAB)

C.
Urgent Change Board (UCB)

D.
Urgent Change Authority (UCA)