Which of the following would be the impact upon a project if the CPI for the project is .75?

Which of the following would be the impact upon a project if the CPI for the project is .75?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is under-budget.

B.
There would be a 25 percent cost decrease.

C.
There would be a 75 percent cost increase.

D.
The project is over-budget.