PrepAway - Latest Free Exam Questions & Answers

Which of the following documents would the project manager update?

The change control board has just approved a request to modify the sampling technique for a project. Which of the following documents would the project manager update?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk management plan

B.
Quality management plan

C.
Communication management plan

D.
Scope management plan


Leave a Reply