Which of the following steps should be taken?

A project has been cancelled during the execution phase. Which of the following steps should be taken?

PrepAway - Latest Free Exam Questions & Answers

A.
Continue to work the project.

B.
Finish the project charter and project plan.

C.
Complete lessons learned document.

D.
Develop the project transition plan.