PrepAway - Latest Free Exam Questions & Answers

Which of the following documents should the team member consult?

The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be completed. Which of the following documents should the team member consult?

PrepAway - Latest Free Exam Questions & Answers

A.
Communication plan

B.
Risk plan

C.
Scope plan

D.
Quality plan


Leave a Reply