Which of the following steps should be taken to formally close a project? (Select TWO)

Which of the following steps should be taken to formally close a project? (Select TWO).

PrepAway - Latest Free Exam Questions & Answers

A.
Finalize the project charter

B.
Create a statement of work (SOW)

C.
Verify client sign-off of the project deliverables

D.
Document the lessons learned

E.
Finalize the work breakdown structure (WBS)