Which of the following should the project manager do?

The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped.
Which of the following should the project manager do?

PrepAway - Latest Free Exam Questions & Answers

A.
Proceed with the release and document the adjustment in the change log.

B.
Proceed with the release and tell the SME the component will be added in a special release.

C.
Delay the release until the component is tested.

D.
Schedule a meeting with the stakeholders to review the impact.