Which of the following would a project manager do NEXT after selecting a vendor for a project?

Which of the following would a project manager do NEXT after selecting a vendor for a project?

PrepAway - Latest Free Exam Questions & Answers

A.
Determine a list of qualified sellers.

B.
Determine vendor resource availability.

C.
Hold a bidders conference.

D.
Negotiate the contract.