Which of the following is a characteristic of fast-tracking a project?

A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?

PrepAway - Latest Free Exam Questions & Answers

A.
Minimizes risk due to decreased timeline.

B.
Requires planning and execution to be completed in parallel.

C.
Minimizes cost since work is completed in four months instead of six.

D.
Requires rework due to decreased timeline.