PrepAway - Latest Free Exam Questions & Answers

Which of the following is the FIRST action they should take?

A project manager needs to replace someone on the project team. Which of the following is the FIRST action they should take?

PrepAway - Latest Free Exam Questions & Answers

A.
Consult the project staffing plan.

B.
Notify the human resources department to open a job posting.

C.
Search for skilled subcontractors who could quickly fill the opening.

D.
Ask the project sponsor for another resource.