A project manager receives a memo from a key stakeholder in the project. The memo states that going forward they should be notified of all scope changes, but not involved in the decision making process. Which of the following should the project manager do NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Initiate a transition plan.

B.
Assign the stakeholder to the change control board.

C.
Schedule a meeting with the stakeholder.

D.
Update the communication plan.