Which of the following will be created during this meeting?

A project manager has determined the probability and impact of identified project risks. A meeting with the project team will be held to determine how to mitigate risks above the project threshold. Which of the following will be created during this meeting?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk response strategies

B.
Risk register

C.
Risk assessment

D.
Stakeholder risk tolerance